A county tender with milestones, commitments and margin
The tender number becomes the project code. The bid becomes the budget. Every supplier commitment and milestone is visible before the margin disappears.
Business profile
- Business
- Civil or building contractor
- Sells
- Contract works
- Operating model
- Awarded tender with milestones and subcontractors

The challenge
- Bid sheet separated from site cost
- Supplier commitments not visible against the budget
- Milestones billed late
- Prefabrication cost outside the contract margin
How it is set up
Open the project
Use the tender number, contract value, customer, dates and project manager.
Plan the cost
Split the budget into material, labour, subcontract, equipment and travel. Add billing milestones.
Commit suppliers
Raise POs for material and subcontract and tag them to the project as commitments. When the supplier bill arrives, tag the bill to the project; the actual cost posts from the bill, not from the PO.
Produce and bill
Use work orders for prefabrication. Record supplier bills as actual cost and bill the achieved milestone.
Daily routine
- Review commitments versus budget
- Match supplier bills to POs
- Update milestone progress
- Check cost before the next certification
Worked numbers
Contract
KES 18,000,000
Committed
KES 6,400,000
Actual cost
KES 4,880,000
Revenue
KES 5,400,000
Margin
KES 520,000
Remaining
KES 13,120,000
Controls that matter
- Commitment is not actual cost
- Supplier bills and timesheets tag the project automatically
- Project P&L reads posted GL lines, not manual entries
- Close WIP before final handover